Stage 1 includes two soccer fields with lighting, fencing and irrigation as well as a soccer pavilion with seating.

The pavilion works are due to commence in May 2022. The multistorey pavilion includes a dual facing grandstand, coaches and media boxes, unisex clubrooms, canteen, function space with balcony and spectator viewing area, a meeting room, training room, first aid and umpires amenities as well as public amenities. 

The total project cost $8.4 million. Construction of the two soccer fields is set to commence mid-year.

Ground floor

  • Main Lobby including lift and stairs
  • Training and coaches Room
  • First aid room and two trainers rooms 
  • 4 change rooms; 2 male and 2 female (can be divided into 8)
  • 2 match officials/umpire change rooms (can be divided into 4)
  • Canteen
  • Grandstand
  • Lift and stairs to the second level of the grandstand
  • Public toilets
     

Second floor

  • Main lobby and viewing balcony
  • Meeting/conference room
  • Male and Female toilets
  • Large social room catering for 180 people
  • Kitchen and bar
  • Viewing balcony and terrace to level two of the grandstand 
  • Grandstand with seating capacity of 520 (450 seats facing main oval and 70 to the second oval)
  • Four coaches/VIP/media boxes

Latest video

 


Concept images

Timeline
  • Works update
    March, 2024

    The soccer pitches have been turfed and are being finalised for use later this year. Both buildings have been completed and surrounding landscaping works are commencing soon. View the progress at https://youtu.be/knpKyr3fFa0

  • Works update
    August, 2023

    The pavilion concrete and steel structures are complete with the roofing being craned into place. Trades are now working on the external brickwork and internal works. 50 kilowatts of solar panels will be installed over the coming weeks with the installation of air conditioning completed. View the progress at https://youtu.be/-Y26_dPVSvs 

  • Works update
    July, 2023

    Drainage and irrigation on the two soccer pitches have been completed. View the progress at https://youtu.be/7uW5T1HHd4U 

  • Works update
    May, 2023

    The first floor to the soccer grandstand has been completed with the frame beginning construction within the coming weeks. The seating has started with the frame and external cladding being finalised. Internal works still also start soon. Irrigation and drainage to the soccer fields is progressing well with concrete and fencing to be installed. View the progress at https://youtu.be/iBggs8j51IA 

  • Works update
    January 2023

    Works continue at the soccer pavillion, with the access ramp to the stands complete, the tanks and pumps installed and the site has been cut to allow for irrigation and drainage to be completed. View the progress at youtu.be/rkK8smUqayw

  • Soccer Pavillion taking shape
    September 2022

    The car park asphalting has been completed and the soccer pavillion will now start to take shape.

  • Works have begun
    April 2022

    Drainage works for Stage 1 have been completed. Placement of fill for the soccer fields has commenced.

  • Pavilion Tender Awarded
    February 2022

    The council awarded the tender for the soccer pavilion at its February meeting. Works are due to commence following the completion of civil works in May 2022.

  • Design tenders awarded
    July, 2020

    Tenders awarded for the design of the soccer pavilion and design of the precinct and fields.