Hereford St bridge

 /  Our Major ProjectsCompleted ProjectsHereford St bridge

Hereford St bridge


PROJECT
COMPLETE

The pedestrian bridge over House Creek (Willow Park, Wodonga) is being replaced with a new, wider bridge.

Works will commence on March 16, 2020 and are expected to take up to six weeks to complete, subject to weather.


Alternative routes

Hereford%20St%20Bridge%20works

Timeline
  • Bridge opened
    April 8, 2020

    The bridge was officially opened just in time for the Easter holidays.

  • Bridge installation
    March 26, 2020

    The first section of the new bridge is being installed. Path and landscaping works are still to be completed.

  • Works have started
    March 16, 2020
    Today works started to the site, demolishing the old bridge to pave the way for the new bridge to be installed