The council received National Stronger Regions Funding from the Federal Government to conduct works in the CBA, which will include the completion of works in High St including landscaping. This would be from Bond to South streets.
Works will begin in the northern end of High St and the intersection with South St in January 2018 .
The works will include the reconstruction of High St from Bond St to South St which will upgrade underground services in the area.
The works will also include landscaping, beautification and new street lighting, the undergrounding of overhead cables and reconstruction of Bond St.
Main features
- Reconstruction of High St from Bond St to South St
- Will remove dip in the road and improve drainage in the area
- Angled parking to remain
- Work will include landscaping, beautification, new street lighting