Wodonga Council
Baranduda Fields Sporting Complex

Page URL: https://www.wodonga.vic.gov.au/Our-Major-Projects/Baranduda-Fields-Sporting-Complex

Baranduda Fields Sporting Complex

 /  Our Major ProjectsBaranduda Fields Sporting Complex

Baranduda Fields Sporting Complex


The Baranduda Fields project is a major regional sporting complex planned for the Baranduda-Leneva Valley.

Set on 100ha of council-owned land, the facility will be the largest regional sporting precinct between Sydney and Melbourne.

The precinct will allow the city of Wodonga to showcase sport at a local, regional and state level, and will provide economic benefits from visitation of major sporting events.

It will also lead to improved physical and mental health for the community through greater participation in sport, and create opportunities for volunteering, social interaction and inclusion.

Extensive public consultation was carried out in 2013, including discussions with more than 25 community and sporting groups, and a study tour was conducted of relevant existing new sports facilities.

Wodonga Council secured $10 million in funding from the Department of Infrastructure, Transport, Regional Development and Communications in March 2020.

The council will be adding a further $10 million in funding over the next three years from the capital works budget to deliver Stage 1 of the project.

Stage 1 will include the following.

The project is set to be completed by mid-2024.


Projects in progress

Video updates


Completed projects

Document Library
Timeline
  • Works update
    March, 2024

    Both soccer buildings have been completed and are being prepared for use. Surrounding landscaping works are yet to take place whilst final works to the ovals are continuing.

  • Works update
    August, 2023

    The third stage of the project is 75 per cent completed with the soccer pavilion structure now complete. The roofing has been craned into place and works have started on the external brickwork and internal framing. 50 kilowatts of solar panels will be installed over the coming weeks with works to continue until December. 

  • Light towers installed
    July, 2023

    The 33m light towers over the football oval have been installed. Drainage and irrigation on the two soccer pitches has also been completed. 

  • Works update
    April 2023

    Stone and sand layers have been added to the oval to assist with future drainage. Chopped cough grass has been fed into trenches to eventually cover the oval by Spring. Fencing and lighting along the oval has also commenced.

    Our soccer pavilion is coming along nicely with the access ramp nearing completion.

  • Changerooms update
    February 2023

    The football and netball facilities are taking shape with the construction of the changerooms commencing. 

  • Car park
    September 2022

    The car park asphalting has been completed.

  • Works update
    April 2022

    All of the site drainage works for stage 1 have been completed. The slab for the 2 netball courts have been poured and works on the roads, car parks, kerb and channelling is under way.

    Gravity sewer has been installed. Placement of fill for the soccer fields has commenced. Construction of the sports fields is set to commence mid-year.

  • Model on display
    March, 2022
    A model of Baranduda Fields showing the scale of the project and stage one is now on display in the council’s Hovell St offices.
  • Works update
    January, 2022
    The intersection to Baranduda Boulevard has been completed and access roads to the site have started to form.
  • Intersection works begin
    September 6, 2021
    Works on the new intersection for Baranduda Fields begin. Pavement widening will be the focus of the initial works.
  • Tender Awarded
    July 20, 2020

    Wodonga Council awarded the tender for the design of the soccer pavilion.

  • Master plan updated, soil testing begins
    January 2021

    An updated master plan was released. Read more on Platform 3690 via the link above.

  • Agreement signed
    March 23, 2020
    The federal funding agreement was signed on March 23, 2020.
  • Council welcomes $10m for Baranduda Fields project
    April 19, 2019
    Wodonga Mayor Cr Anna Speedie has welcomed the $10 million confirmed funding from the Australian Government for Baranduda Fields.